All shelving units are up & most of the "renovation" work is done...
I know it's been a while since my last update here but until now there wasn't much to show. This past Wednesday two trucks of fixtures were delivered. Thursday the crew arrived to set them up. The crew of seven assembled all the shelving in 1 1/2 days, they were a pleasure to watch (see pics below). Also on Thurs. the computer company came to start the installation setting up our main server and a work station. In addition we are able to get to the internet via a wireless laptop and the painters put the finish coat on the walls.
Next Tuesday the first of six trucks of merchandise will be delivered, with two each week. Monday some of the new staff will start. So far everything is coming together nicely. Many comments from people in the area basically saying...
" they can't wait to have a hardware store back"